Building an extension step by step: the stages on site, in order
· 12 min read

An extension is built from the ground up, and each stage is covered by the next: the foundations by the floor, the walls by the roof, the cables and pipes by the plaster. So the order matters, and so do the checks made before anything is hidden. This guide follows a single storey rear or side return extension on a London house, from the first day on site to the day building control signs it off.
A single storey rear extension usually takes around three to four months on site, once planning is in place and the design is agreed. The steps before that, the design, the planning route and the party wall notices, are in our guide to planning a house extension step by step.
Our serviceFrom The MVV, a family business of builders in Chiswick. This guide is part of our work on house extensions in London.
The stages of building an extension, in order
Building an extension runs in this order:
- Before the first day: consents, notices, drawings and long lead orders.
- Setting up the site: protection, access, the skip, and clearing what stands in the way.
- Foundations: digging and pouring them.
- Drains: new or diverted drains, laid and inspected before they are buried.
- The floor: walls up to the damp proof course, then the ground floor slab.
- The shell: the walls, the steel beams and the roof.
- Weathertight: windows, doors and rooflights in, so the inside stays dry.
- The knock through: the old back wall opened into the new room.
- First fix: cables, pipes and any underfloor heating, before the walls are closed.
- Plaster and screed: the walls and ceilings finished, the floor levelled.
- Second fix: the kitchen, the floor, the electrics and plumbing connected, then decoration.
- Outside: the patio and the garden made good.
- Sign off: building control's completion certificate, snagging and handover.
Before the first day on site
Most of what decides how smoothly an extension is built is settled before anyone digs. By the first day you want:
- Planning permission, with any conditions that must be met before work starts. Under permitted development there is no application, except prior approval for a larger single storey rear extension.
- Party wall notices served in time: two months for work to a party wall, such as a beam bearing into it, and one month for a new wall on the boundary or for digging near a neighbour's foundations. Each neighbour's written consent, or a surveyor's award, has to be in place before the work it covers starts.
- Building regulations approval arranged, with the engineer's structural design ready, because building control checks every beam and foundation against it.
- A build over agreement from Thames Water, where the extension is close to a public sewer.
- An asbestos survey where it is needed: HSE guidance says any home built or refurbished before 2000 may contain asbestos, and old lean-tos and conservatory roofs are a common place to find it.
- The health and safety appointments: a principal designer and a principal contractor, appointed in writing.
- The drawings and the specification finished, so the builder works from information rather than guesses.
- Long lead items ordered early: glazed doors, rooflights, the steel beams and the kitchen, with the final measurements taken on site where they need them.
Our checklist of what has to be in place before work starts goes through each item and how long it takes.
Stage 1: setting up the site
The site is set up before anything comes down: the working area fenced off, a skip or a grab lorry arranged, and the parts of the house the trades will walk through protected. On a terrace with no side access, everything comes and goes through the house, so the protection runs from the front door to the garden. A skip on the road needs a licence, which the skip company usually obtains, and scaffolding or hoarding on the pavement needs one from the council. Tell the neighbours what is coming and when, with a name and a number for the site.
Any old conservatory, lean-to or shed where the extension will stand is taken down now.
Stage 2: the foundations
The ground is dug out for the foundations to the depth and width on the engineer's drawings. The depth depends on the soil, on nearby trees, whose roots can dry out and shrink London clay, and on the neighbours' foundations: digging within 3 metres of a neighbour's building and deeper than its foundations needs one month's party wall notice.
Building control sets the stages it wants to see, and for an extension they usually begin here, with the open trenches before the concrete goes in. What the dig finds is the first real test of the budget: old drains, roots, a buried wall or softer ground than expected can mean digging deeper, which is priced when it is found. A typical single storey extension stands on concrete strip or trench fill foundations; where the ground is poor, the engineer may design piles or a raft instead, which changes both the price and the programme.

Stage 3: the drains
New drains go in while the ground is open: the rainwater from the new roof, and the kitchen waste if the sink moves. On many London terraces the existing drains run under the garden or down the side return, so they may have to be diverted, or the extension built over them. Building control usually inspects new drains before they are covered. Thames Water, which serves most of London, says a build over agreement is likely to be needed for work within 3 metres of a public sewer or 1 metre of a public lateral drain, and that is arranged before work starts, not when the trench is already open.
Stage 4: up to the damp proof course, then the floor
The walls are built up from the foundations to the damp proof course, at least 150 mm above the ground outside, which stops moisture rising into the walls. Inside them, the ground floor is built: usually compacted hardcore, a damp proof membrane, insulation and a concrete slab, or a suspended floor of beams and blocks. Building control will usually want to see the damp proof course and the concrete over the site before they are covered.
The level of the new floor is set now. It has to meet the floor of the house once the screed and the finish are on top, or there will be a step where the old room meets the new.
Stage 5: the walls, the steels and the roof
Above the damp proof course the walls go up, in brick and block or as a timber frame: our guide to timber frame or brick compares them. The steel beams go in as the walls rise: the beams that carry the roof over a wide glazed opening and, on a side return, the beams that replace the side wall of the back addition, with the walls above supported while that work is done. Each beam is sized by the engineer and checked by building control.
Then the roof. A flat roof is built from timber joists, a deck, insulation and a waterproof membrane, with any rooflights set into it. A pitched or glass roof follows the same order with different materials, and our glass extensions guide covers the glazed options.

Stage 6: weathertight
Once the roof is on and the windows, doors and rooflights are fitted, the shell is weathertight, and the work inside can go on whatever the weather. Glazed doors and rooflights are made to measure, so they are ordered early and measured on site once the openings are built: a shell that is waiting for its doors is a shell the rain can get into.

Stage 7: the knock through
The old back wall of the house often stays in place until the new room is weathertight, so the house stays secure and warm through the messiest part of the build. Then it is opened up: the floors above are propped with temporary supports, the wall comes out, padstones go in at each end and the steel beam is lifted into place. Building control inspects it, and the steel is boxed in or coated for fire protection. On some jobs the beam goes in earlier, as the extension is built, and the wall below it comes out later. Where the beam bears into a party wall, that is work to the party wall, which needs two months' notice. Our guide to knocking through a wall goes through it step by step.
From here until the new kitchen is working, the back of the ground floor is a building site, so plan where you will cook and eat for those weeks.
Stage 8: the first fix
With the room closed in, the services go in. The electrician runs the cables and fixes the back boxes for every socket, switch and light; the plumber and heating engineer run the water, waste and heating pipes; and underfloor heating pipes are laid on the slab, ready for the screed. Every position is decided now, because after the plaster a socket in the wrong place means cutting into a finished wall. Our guide to deciding early lists the choices to make before this stage, and what is second fix explains the difference between the two fixes.
Stage 9: insulation, plaster and screed
Most of the insulation is already in, built into the walls, the roof and the floor as they went up. Any that remains goes in now, often as insulated plasterboard, and the walls and ceilings are plastered, or boarded and skimmed. The floor gets its screed, a levelling layer over the slab that also holds any underfloor heating pipes. A screed has to dry before a timber or tiled floor goes on top of it, and the floor layer checks it first: a floor laid on a screed that is still wet can lift or crack later.
Stage 10: second fix, the kitchen and decoration
The trades come back to finish. The floor goes down first where it runs under the units, then the kitchen units go in, with stone worktops templated once the base units are fixed; the electrician fits the faceplates and lights, and the plumber connects the sink, taps and radiators. Then the decorator fills, sands and paints. The same sequence across a whole house is set out in our guide to the order of works for a renovation.
Stage 11: outside
The garden is finished once the heavy work no longer needs it, because it is where the skip, the mixer and the materials have stood. The patio or terrace is laid to fall away from the new doors, with the drainage it needs, and the ground around the extension is made good. At St Germans Place in Blackheath, the work outside was laying the external tiles and the landscaping, so the new kitchen opens onto a small patio.
Stage 12: completion, snagging and handover
When the work is finished, building control makes a final inspection and issues a completion certificate, which confirms building control is satisfied that the work meets the Building Regulations. Where a private building control approver checked the work, it issues a final certificate instead. Keep it with the property's papers, because a buyer's solicitor will ask for it when you sell. The electrician's certificate, and a gas certificate for any gas work, come at the same time.
Then the extension is walked with the builder and every defect is listed: the snagging list, which the builder puts right. Handover brings the certificates, the guarantees for the glazing, the roof and the appliances, and the manuals.
How long does it take to build an extension?
A single storey rear or side return extension usually takes around three to four months on site, once planning is in place and the design is agreed. Our rear extension at St Germans Place in Blackheath, dug down below the garden, took four months as a project. A two storey extension, a basement under the house, or an extension built together with a refurbishment of the rest of the house takes longer.
What stretches a programme:
- What the dig finds: old drains, roots, buried walls or poor ground.
- Made to order items that arrive late: glazed doors, rooflights, steel and the kitchen.
- Weather, while the foundations are open and before the roof is on.
- Decisions made late, so trades wait or finished work is redone.
- Work covered up before building control has seen it, which may have to be opened up again.
Before work starts, allow for the clocks that run before the build:
- The design and the drawings, which move at the pace of your decisions.
- Party wall notices: one or two months, depending on the work.
- Building control: a full plans application is decided within five weeks, or longer if you agree.
- Planning, where it is needed: a householder application has an eight week target.
The steps before the build, in order, are in our guide to planning a house extension step by step.
Living at home while an extension is built
It is often possible to stay at home through a single storey extension, because the noisy, dusty work happens outside the house until the knock through. The hardest weeks are from the knock through until the new kitchen is working. Plan for them before work starts: a temporary kitchen in another room, somewhere to eat, and how children and pets will be kept away from the work. Agree the working hours, deliveries and parking with the builder, and keep the neighbours informed as the work moves on.
Who you will see on site
An extension is built by a sequence of trades: groundworkers for the dig, the foundations and the drains; bricklayers; the team that installs the steel beams; a roofer; the glazing installer; an electrician; a plumber and heating engineer; a plasterer; a floor layer; the kitchen fitter; and a decorator. Behind them, the structural engineer designs what holds it up and building control checks it. Our guide to your project team explains who does what. With design and build, one team takes the extension from the first drawings to the completion certificate.
Getting started
If you are at the start, price the building work with our free estimate, which gives a range for your own size, shape and finish in about two minutes, and read how much an extension costs. Our house extensions page shows how we design and build extensions across London, and when you are ready to talk about yours, get in touch.
Good to know
Frequently asked questions
- What are the stages of building an extension?
- Setting up the site, then the foundations and drains, the walls up to the damp proof course and the floor slab, the walls, steel beams and roof, the windows and doors, and the knock through into the house. Then come the first fix of cables and pipes, the plaster and screed, the second fix with the kitchen, floor and decoration, the garden, and finally building control's completion certificate, snagging and handover.
- How long does it take to build an extension?
- Around three to four months on site for a typical single storey rear or side return extension, once planning is in place and the design is agreed. A two storey extension, a basement under the house, or an extension built alongside a wider refurbishment takes longer. Before the build, allow for the design, one or two months of party wall notices, up to five weeks for a full plans building control decision and, where it is needed, eight weeks for planning.
- When does building control inspect an extension?
- At the stages it chooses, which for an extension usually include the foundation trenches before the concrete is poured, the damp proof course and the concrete laid over the site, and new drains before they are buried. The steel beams are checked against the engineer's design, and a final inspection when the work is finished leads to the completion certificate.
- When is the back wall knocked through on an extension?
- Often once the extension is weathertight, with its roof, windows and doors in, so the house stays secure and warm for as long as possible. The floors above are propped, the wall is taken out, a steel beam goes in, and building control inspects it before it is boxed in or coated for fire protection.
- Can I stay in my house while an extension is built?
- Often, yes, for a single storey extension, because most of the work happens outside the house until the knock through. The hardest weeks are from the knock through until the new kitchen is working, so plan a temporary kitchen and agree working hours and access with the builder before work starts.
- What is a completion certificate for an extension?
- The certificate building control issues after its final inspection, confirming it is satisfied that the extension meets the Building Regulations. Where a private building control approver checked the work, it is called a final certificate. Keep it with the property's papers: a buyer's solicitor will ask for it when you sell.